With the holidays almost over, hopefully the work will start again on Monday. The electrician has been here over some of Christmas, and all the tracking is done, and some conduit installed.

Posted Mon Jan 5 08:18:59 2004
Inside - 03 Jan 2004

The electrician came over on Thursday 18th December, and it took around 3 hours for us to mark out all the electrical points. Lightswitches, powerpoints and tv etc all had to be marked. Then on Monday 22nd a man came to do the tracking. He worked all day monday, and Wednesday, then came back again on Monday 29th.

The electrician has been back several times over the holiday period fitting boxes, and conduit - now most of that work is complete. He will return once the roof is on to start wiring the upstairs. Downstairs needs to be battened before he can go any further there.

Roof - 03 Jan 2004

The facia work was completed just before the holidays, hopefully the felt can go on as soon as the workers return.

Electrical Work - 03 Jan 2004

The electrician came over on Thursday 18th December, and it took around 3 hours for us to mark out all the electrical points. Lightswitches, powerpoints and tv etc all had to be marked. Then on Monday 22nd a man came to do the tracking. He worked all day monday, and Wednesday, then came back again on Monday 29th.

The electrician has been back several times over the holiday period fitting boxes, and conduit - now most of that work is complete. He will return once the roof is on to start wiring the upstairs. Downstairs needs to be battened before he can go any further there.