Diary - 15 Oct 2003 - Service Connections

<<< Tue 14 Oct - NIE Connection Oct 2003 Thu 16 Oct - Brickwork continues >>>
Wed 15 Oct - Service Connections

Today the digger was here to dig a track for the electricity cable, from the pole to the house. All the services were to be laid in the same track, so there were two water pipes (one for spring water) and the phone cable. [more] The brickwork also continued [more].

Posted Thu Oct 16 06:49:48 2003
Brickwork - 15 Oct 2003

The brickies arrived back today, some more progress, and some internal walls.

Electrical Work - 15 Oct 2003

The phone had been installed by BT into the caravan, and a reel of cable was left which should reach to the house. I had to remove the cable from the caravan, as it was to be laid down with the water/electricity.

Caravan - 15 Oct 2003

Driveway - 15 Oct 2003

© Copyright 2004-2007 - Simon McCaughey -