Thu 22 Jan - Roof Complete

The tilers came back on Monday, and by the end of the day the tiling had been completed around the velux windows, and the lead flashing of the porch. Tuesday finished the rest of the roof, and by Wednesday the conservatory had been felted, battoned, and tiled. [more]

The joiners were also here Monday and Tuesday battening the ceilings downstairs. This means the electrical work can now be completed downstairs. [more]

Posted Fri Jan 23 08:02:36 2004
Inside - 22 Jan 2004

The joiners were here Monday and Tuesday battening the ceilings downstairs. This means the electrical work can now be completed downstairs.

The external doors were sealed below with a lintil.

The electrician has been here Wednesday and Thursday night, working at completing the first fix downstairs. I have also been installing cabling for an alarm system too.

Roof - 22 Jan 2004

The tilers came back on Monday, and by the end of the day the tiling had been completed around the velux windows, and the lead flashing of the porch. Tuesday finished the rest of the roof, and by Wednesday the conservatory had been felted, battoned, and tiled.

Electrical Work - 22 Jan 2004

The electrician has been here Wednesday and Thursday night, working at completing the first fix downstairs. I have also been installing cabling for an alarm system too.

Caravan - 22 Jan 2004

Driveway - 22 Jan 2004

View - Side - 22 Jan 2004

View - Road - 22 Jan 2004

View - Back - 22 Jan 2004