Brickwork

Tue 09 Dec - Brickwork complete!

The brickies returned for one day (yesterday) and finished off the inside walls. They also did a good tidy up, there were a lot of broken blocks, and little piles of cement. Now we are ready for the roof!

Sat 06 Dec - Brickwork almost complete

Wed 03 Dec - Upstairs - more progress

Sat 29 Nov - Upstairs - second week completed

Two weeks work upstairs, the gable walls are well up, the windows almost complete at the front, and the final lift of blocks through the back wall was delivered yesterday.

Hopefully the incoming week will finish the work, weather allowing, the roof is ordered and should be ready in a week. The house should be sealed by Christmas.

Fri 21 Nov - Upstairs - first week completed

One weeks work upstairs, and we are ready for cills at the front. An area around the bathroom has been left down at the back to allow more blocks to be lifted up when required.

The fireplace has also been completed along with the gable wall in the living room.

Thu 20 Nov - Upstairs continues...

Wed 19 Nov - Upstairs continues

A little more progress - photos taken at lunchtime, so hopefully there will be a lot more progress by the weekend. The forecast for the rest of the week is fairly good. The brickies think that 2-3 weeks will complete it depending on weather.

Tue 18 Nov - Upstairs starts!

You will notice a deteriation in the quality of the pictures - this is because most are now taken in poor lighting conditions. Unfortunately it is now pitch dark when I arrive home (5pm) as the first pic shows. The others were taken at 8am - they look a bit grainy because they are corrected for brightness.

Thu 06 Nov - Bison slabs laid

At last the slabs have arrived, and 2 hours put them on. There are a couple of pics here, but follow the full progress here.

Mon 20 Oct - A little progress

Fri 17 Oct - Conservatory brickwork

Thu 16 Oct - Brickwork continues - internal walls

Wed 15 Oct - Brickwork continues - 1st floor at front

The brickies arrived back today, some more progress, and some internal walls.

Mon 13 Oct - Brickwork continues - 1st floor at back

Fri 10 Oct - Brickwork continues - Lintil level

This has been a week of slow progress, lots of rain and miserable weather. However they are now ready to put lintils on at the back, and another couple of days should see a lot of progress. Once the building is up to first floor level there will be a two week delay while the concrete slabs are made. The company has to come out and measure, and then make them as they won't trust drawings!

Wed 08 Oct - Brickwork continues

For the most of the morning it rained, so progress was slow.

Tue 07 Oct - Sill level

Today turned out to be a milder, calmer, drier day. Some sills are set, others ready to be set - hopefully it will be good again tomorrow.

Mon 06 Oct - Brickwork started

The brickwork has started, and the weather has changed. Over the weekend we saw gale force winds, and persistant rain. Hopefully this is not the pattern for the winter...