Interior work

Wed 28 Apr - Joinery complete

Tue 27 Apr - Sheeting complete

Mon 26 Apr - Tiling continues

Sat 24 Apr - Kitchen wall tiled

Fri 23 Apr - More arcitrave

Thu 22 Apr - Delays

Wed 21 Apr - Arcitrave on

Tue 20 Apr - Sanitaryware delivered

Mon 19 Apr - Most doors on

Sat 17 Apr - First coat of paint finished

Fri 16 Apr - Cleaning starts

Thu 15 Apr - Doors arrive

Tue 13 Apr - Dry-lining

Fri 09 Apr - Banister & fireplace

Thu 08 Apr - Kitchen complete

Wed 07 Apr - Hot water tank installed

Sat 03 Apr - Painting

Posted Mon Apr 5 08:21:42 2004
Thu 01 Apr - Kitchen stopped

Work has stopped on the kitchen, the screws for the door handles have not arrived! The fitter will be back sometime next week to finish off.

Posted Mon Apr 5 08:21:42 2004
Wed 31 Mar - Kitchen doors on

Tue 30 Mar - Kitchen fitting continues

Mon 29 Mar - Kitchen going in

Fri 26 Mar - Ready for kitchen

Wed 17 Mar - Floors started

Sat 13 Mar - Stud walls up

Thu 11 Mar - Fireplace brickwork complete

Wed 10 Mar - Plumbing continues

The chrome radiator arrived from screwfix yesterday, so I took it to the plumber today for measurements.

Tue 09 Mar - Radiators and Stairs

The stove for the living room also arrived today.

Mon 08 Mar - Underfloor work continues

The electrician also marked all the walls where there are conduits inside, so that when the joiners come to place the skirting, they don't hit them.

The radiators and pipes have arrived for the heating.

Thu 04 Mar - Plasterwork complete

Sat 28 Feb - Downstairs ceilings completed

Saturday morning, and the plasterers are back, the ceilings of all the downstairs rooms are now done.

Fri 27 Feb - Upstairs plaster completed

The plasterers have plastered the ceiling and almost all the walls of the landing, and the slingsby stairs have been installed too. Another part of a day will finish the work upstairs, so all that remains is downstairs.

Fri 13 Feb - Plaster bands at back

With the plasterers working outside all week there has been minimal progress inside. They have however got most of the remaining window cills ready.

Mon 09 Feb - Bedroom ceilings complete

The plasterers skimmed the ceilings of the bedrooms and the bathroom today.

Sat 07 Feb - Plasterers get ready for ceilings

Another week inside has been completed, and the plasterers are ready to start on the ceilings on Monday, if the weather is bad. If the weather is good the plasterers will work to get the outside completed, as the contractor needs the scaffolding elsewhere.

Sun 01 Feb - Some more pics

Sat 31 Jan - Holes cut for lights

The electrician came today to cut holes in the plasterboard for the lights in the kitchen and conservatory, to ensure that the cables were hidden where we expect them. All were marked carefully, and the cables were there, phew!

Fri 30 Jan - Plaster inside

Wed 28 Jan - Plasterboard

Sat 24 Jan - Downstairs - battens and first fix almost complete

Thu 22 Jan - Downstairs - battens and first fix

The joiners were here Monday and Tuesday battening the ceilings downstairs. This means the electrical work can now be completed downstairs.

The external doors were sealed below with a lintil.

The electrician has been here Wednesday and Thursday night, working at completing the first fix downstairs. I have also been installing cabling for an alarm system too.

Fri 16 Jan - Pics of inside

Just some pictures of inside, now that the roof is felted.

Sat 03 Jan - Holidays almost over

The electrician came over on Thursday 18th December, and it took around 3 hours for us to mark out all the electrical points. Lightswitches, powerpoints and tv etc all had to be marked. Then on Monday 22nd a man came to do the tracking. He worked all day monday, and Wednesday, then came back again on Monday 29th.

The electrician has been back several times over the holiday period fitting boxes, and conduit - now most of that work is complete. He will return once the roof is on to start wiring the upstairs. Downstairs needs to be battened before he can go any further there.