Subfloor

Mon 29 Sep - Filling levelled

Wed 24 Sep - Subfloor complete

Tue 23 Sep - mesh laid

Mon 22 Sep - Ducting laid

The contractor was here today to lay ducting and soil pipes which go below the sub-floor.

Sat 20 Sep - Nothing happening...

Not much change here, but a lot of filling has arrived for the inside of the house. It looks like good topsoil, but it is actually just dried clay. The view from the rear gives an idea of the finished ground level.

Wed 11 Sep - Footings continued...

Wed 10 Sep - Footings continued...

Mon 08 Sep - Footings underway

The foundations have set, and the construction of the footings is underway