View from the caravan
Thu 29 Apr - Cleaning complete
Thu 04 Mar - Plasterwork complete
Fri 27 Feb - Upstairs plaster completed
Fri 13 Feb - Plaster bands at back
Sat 07 Feb - More filling
Sun 01 Feb - Back wall plastered
Sat 24 Jan - Ready for plaster
Thu 22 Jan - Roof Complete
Sat 17 Jan - Chimneys Dashed
Fri 16 Jan - No Progress
Fri 09 Jan - Roof felt complete
Wed 07 Jan - Roof felt on
Sat 03 Jan - Holidays almost over
Wed 17 Dec - Facia work continues
Sat 13 Dec - Scaffolding up
Sat 06 Dec - Brickwork almost complete
Sat 29 Nov - Upstairs - second week completed
Fri 21 Nov - Upstairs - first week completed
Wed 19 Nov - Upstairs continues
Tue 18 Nov - Upstairs starts!
Thu 06 Nov - Bison slabs laid
Fri 17 Oct - Conservatory brickwork