Thu 29 Apr - Cleaning complete
Fri 02 Apr - Downpipes installed
Fri 26 Mar - Groundworks complete
Wed 24 Mar - Topsoil tidyup
Tue 23 Mar - Drains filled in
Thu 04 Mar - Plasterwork complete
Fri 27 Feb - Upstairs plaster completed
Fri 13 Feb - Plaster bands at back
Sat 07 Feb - More filling
Sun 01 Feb - Back wall plastered
Sat 24 Jan - Ready for plaster
Thu 22 Jan - Roof Complete
Fri 16 Jan - No Progress
Fri 09 Jan - Roof felt complete
Sat 03 Jan - Holidays almost over
Sat 13 Dec - Scaffolding up
Sat 06 Dec - Brickwork almost complete
Fri 21 Nov - Upstairs - first week completed
Tue 18 Nov - Upstairs starts!
Thu 06 Nov - Bison slabs laid
Fri 17 Oct - Conservatory brickwork
Thu 16 Oct - Brickwork continues - internal walls
Wed 15 Oct - Brickwork continues - 1st floor at front
Mon 13 Oct - Brickwork continues - 1st floor at back
Fri 10 Oct - Brickwork continues - Lintil level
Wed 08 Oct - Sill level
Tue 07 Oct - Sill level
Mon 06 Oct - Brickwork started
Tue 30 Sep - Filling levelled
Wed 24 Sep - Subfloor complete
Tue 23 Sep - Mesh laid
Sat 20 Sep - No progress
Wed 11 Sep - Subfloor almost complete
Wed 10 Sep - Subfloor almost complete
Mon 08 Sep - Footings underway
Thu 04 Sep - Bricks arrived
Mon 01 Sep - Driveway stoned
©